29 February 2016

This week at Campbell's Corner Refurbishment

1st Floor

  • Finishing of works including painting, electrical and air-conditioning;

 External

  • Awning works continuing; and
  • Painting to external facade continuing.

Traffic at times along Bridge St in front of Campbell’s Corner will be reduced to one lane to allow for awning works.

Footpath works along Brook Street continuing with changed pedestrian access at Newcastle Permanent corner.

Works include:

  • Installation of tree pits in Brook St; and
  • Planting of gardens and installation of irrigation.

A weekly site meeting regarding footpath works is held at 8:45am each Friday, in Shop 2 Campbell’s Corner (previously occupied by Nora and Kate).  All interested parties are encouraged to come, where a briefing will be given on the scheduled work activities for the coming week and have an opportunity to ask questions or discuss any concerns.

For any additional information on the footpath works please contact Kellie Scholes – Project Manager 0407 252 142.

22 February 2016

This week at Campbell's Corner refurbishment:

1st Floor

  • Laying of carpet;
  • Electrical finishing;  

External 

  • Awning works continuing; and
  • Painting to external facades continuing.

Traffic along Bridge St in front of Campbell’s Corner will be reduced to one lane to allow for awning works.

Footpath works along Brook Street continuing with changed pedestrian access at Newcastle Permanent corner.

A weekly site meeting regarding footpath works is held at 8:45am each Friday, in Shop 2 Campbell’s Corner (previously occupied by Nora and Kate).  All interested parties are encouraged to come, where a briefing will be given on the scheduled work activities for the coming week and have an opportunity to ask questions or discuss any concerns.

For any additional information on the footpath works please contact Kellie Scholes – Project Manager 0407 252 142.

 

1st February 2016

This week at Campbell's Corner Refurbishment

Works for this week include:

Ground Floor

  • Final tiling works to enable public access through arcade;
  • Installation of fixtures and fittings to open public toilets;

1st Floor

  • Air-conditioning continuing;
  • Electrical and communications continuing;  

External 

  • Painting to external facades continuing; and
  • Installation of frieze on awning along Brook St. 

Footpath works along Bridge Street continue. Midweek works will switch from alongside the building to the kerb with pedestrian access managed.

A weekly site meeting regarding footpath works is held at 9.30am each Friday, in Shop 2 Campbell’s Corner (previously occupied by Nora and Kate).  All interested parties are encouraged to come, where a briefing will be given on the scheduled work activities for the coming week and have an opportunity to ask questions or discuss any concerns.

For any additional information on the footpath works please contact Kellie Scholes – Project Manager 0407 252 142.

 

This week at The Upper Hunter Tertiary Education Centre

The construction project is reaching completion with final commissioning to take place in March following the installation of the electrical kiosk.

The following completion work planned this week:

  • Final landscape works;
  • Defect inspections; and
  • Authority inspections.

The pad footing for the kiosk will be poured this week.

8 February 2016

This week at Campbell's Corner

Ground Floor

  • Final tiling works to enable public access to car park terrace (available midweek);
  • Cleaning of new public toilets for public access (available midweek);

1st Floor

  • Air-conditioning continuing;
  • Electrical and communications continuing;  

External

  • Awning works continuing;
  • Painting to external facades continuing; and
  • Installation of frieze on awning along Brook St.

Footpath works along Bridge Street continuing. Changed pedestrian access between Westpac Bank and Newcastle Permanent on Tuesday and Wednesday with works to commence in Brook St the following week

A weekly site meeting regarding footpath works is held at 8:45am each Friday, in Shop 2 Campbell’s Corner (previously occupied by Nora and Kate).  All interested parties are encouraged to come, where a briefing will be given on the scheduled work activities for the coming week and have an opportunity to ask questions or discuss any concerns.

For any additional information on the footpath works please contact Kellie Scholes – Project Manager 0407 252 142.

18 January 2016

This week at Campbell's Corner Refurbishment

Tenants of Campbell’s Corner are communicated with frequently about the works but the intention of this email is to keep neighbouring businesses and community informed on the works scheduled for the week ahead. 

The majority of downstairs retail works are to be completed by the end of January with the upstairs work to be completed by end of February.  

The footpath works along Bridge St are planned to recommence from Monday 25 January.

Ground Floor

  • Toilet fixtures installation continuing;
  • Tiling continuing including entrances;

1st Floor

  • Painting continuing;
  • Air-conditioning continuing;
  • Electrical rough-in continuing;

External

  • Painting to external facades continuing; and
  • Installation of the frieze along Bridge St commencing this week.

This week at Upper Hunter Tertiary Education Centre

With the exception of the new electrical kiosk the construction works are nearing completion. The electrical kiosk works are to be completed in March.

The following completion work planned this week:

  • Landscaping;
  • Painting; and
  • Hydraulic works.